Transport · Map · 6 min read
Alto's High-Speed Rail Map: Seven Stops, a 15-km Tunnel and 130 km of Canadian Shield
Alto plans a Toronto to Québec City line with seven stops, but has not published an alignment. The Parliamentary Budget Officer's cost estimate of 75 to 113 billion dollars names the two stretches it treats as cost drivers: a tunnel under Mount Royal and the Canadian Shield.
Updated Nov. 12 with the expropriation law promised in Budget 2026, Alto's construction timeline and its field surveys between Ottawa and Montréal.
What's new: a law to take land faster
Budget 2026 says the government will bring in a law to speed up construction of Alto. In the budget's words, the law "will streamline expropriation activities and enable early preconstruction work." Expropriation is the legal process that lets the government take private land for a public project, with compensation.
Alto says the line will first try to follow existing roads, railways and power lines to limit the impact on homes and farms. Where it cannot, Alto says it will acquire property, through expropriation if needed.
Where will Alto's high-speed rail run?
Alto, the federal Crown corporation planning Canada's high-speed rail line, says it will stop in Toronto, Peterborough, Ottawa, Montréal, Laval, Trois-Rivières and Québec City, across Ontario and Quebec. But the exact proposed route has not been published.
The map above is therefore a schematic, not the proposed alignment. It joins the seven planned stops in order so the geography is easier to see. Alto has shown only a generalised view of its route and has not released station sites.
The Parliamentary Budget Officer (PBO) has published enough to show where construction could get particularly difficult: about 130 km of Canadian Shield terrain between Ottawa and Peterborough, plus a 15 km tunnel under Mount Royal between Montréal and Laval.
Alto stops: the seven planned stations
From west to east:
- Toronto
- Peterborough
- Ottawa
- Montréal
- Laval
- Trois-Rivières
- Québec City
Kingston is a possible eighth stop. The government asked Alto in June to study it (see below). Alto has not published the exact site of any station.
Where will Alto run through Ottawa?
Ottawa to Montréal, about 200 km, is the first section the government and Alto plan to build. Alto and its private partner Cadence say they have completed more than 1,000 field surveys along that stretch this year, including drone flights over sites in the study corridor that run through the end of 2026.
Alto has not released the route through Ottawa or the location of the Ottawa station. It says access to private land for surveys is voluntary, and that no drone flies over private property without the owner's permission.
When will Alto be built?
- Start: construction on Ottawa to Montréal is expected to begin in 2029 to 2030, according to Alto.
- Each section: 7 to 10 years to build, Alto says.
- Full line: about twelve years, built in sections that overlap.
Alto says it is too early to give construction dates for Ottawa to Toronto or Montréal to Québec City.
How long is the line?
Alto describes the line as "approximately 1,000 km of dedicated and electrified tracks" for trains running at 300 km/h or more. The PBO assumes less. It uses 850 km as "an upper-bound assumption for the length of new track", noting that the driving distance from Toronto to Québec City via Montréal and Ottawa is under 850 km.
As a simple geographic check, the straight-line distances between the seven city-centre points add up to about 773 km (Toronto to Peterborough 112, Peterborough to Ottawa 242, Ottawa to Montréal 167, Montréal to Laval 16, Laval to Trois-Rivières 122, Trois-Rivières to Québec City 114). A real rail alignment would be longer, which makes the PBO's 850 km upper-bound assumption plausible. The gap between 850 and 1,000 km matters: the government's 60 to 90 billion dollar estimate is 71 to 106 million dollars per kilometre over 850 km, but 60 to 90 million over 1,000 km.
How much will Alto high-speed rail cost?
The PBO estimates 75 to 113 billion dollars, against the government's 60 to 90 billion. It names two stretches as the main cost drivers.
The Canadian Shield, between Ottawa and Peterborough. The PBO says about 130 km of this stretch could encounter Canadian Shield terrain, not necessarily continuous rock cutting. To meet the alignment that 300 km/h trains need, the report assumes extensive rock cutting, grading and filling. It treats each 1.3 km of Shield as equal to 1 km of elevated structure, which turns the 130 km into 100 km of elevated structure in its model. The PBO prices each additional kilometre of elevated structure at 153 million dollars (range 132 to 175 million). At that rate, those 100 km are worth roughly 15 billion dollars. That figure applies the PBO's rate; the report does not print it. The PBO says rock cutting costs less than elevated track, which is why it counts 1.3 km of rock as 1 km of elevated structure.
A tunnel under Mount Royal. The PBO assumes about 15 km of tunnel to connect Laval and Montréal. The PBO prices each additional kilometre of tunnel at 169 million dollars (range 142 to 196 million), so the tunnel is worth about 2.5 billion dollars, again a multiplication of the PBO's rate, not a figure it publishes.
Applying the PBO's rates to those assumed quantities gives roughly 18 billion dollars, a figure the PBO does not publish itself. The two items are already part of the PBO's 75 to 113 billion dollar estimate (88 to 133 million dollars per kilometre), not an extra cost on top of it. The rest of the line is assumed to be cheaper. The PBO describes Montréal to Ottawa as "relatively straightforward" along the Ottawa River lowlands, and Montréal to Québec City as following the St. Lawrence lowlands with "little requirement for viaducts", though bridges will be needed in places.
The Kingston option
On June 22, 2026, the government directed Alto to assess a southern route between Peterborough and Ottawa with a possible stop in Kingston. The PBO says this could add about 50 km, but would be more level and avoid more of the Canadian Shield. The government has not released a revised cost for it, and the PBO did not cost it.
A straight-line check agrees on the length. Peterborough to Ottawa direct is 242 km. Going through Kingston is about 293 km, roughly 50 km more.
What to watch
The exact route is still to be set, and it will decide how much of the line runs through rock. The Kingston assessment is the one to watch. The PBO says that route is more level and avoids more of the Canadian Shield, but it is about 50 km longer and passes through more settled and ecologically sensitive land, including the Frontenac Arch Biosphere. The PBO says this would bring more land acquisition, mitigation and consultation.
The next thing to watch is the route itself. The budget's faster expropriation law matters most to people who own land along the line, and until Alto publishes the Ottawa to Montréal alignment and its station sites, nobody along the corridor knows whether their land is in the way. For the full cost comparison with 94 high-speed lines worldwide, see the Alto high-speed rail cost analysis.